Below is a high-level milestone schedule including deliverables and subtasksProject kickoff- 12/10/16Develop Week 1 content- 12/20/16Develop Week 2 content- 1/20/17Develop Week 3 content- 2/6/17Status Update to Stakeholders - (Deliverable due 2/6/17)Create pre-test- 2/6/17Develop Week 4 content- 2/24/17Develop Week 5 content- 3/20/17Develop Week 6 content- 4/14/17Status Update to Stakeholders - (Deliverable due 4/14/17)Develop Week 7 content - 5/20/17Purchase equipment for students- 5/20/17Content Design Review with Stakeholders- (Deliverable due 06/05/17)Include feedback from Stakeholders in course content- 07/14/17Initiation of Pilot Course- 08/14/17Completion of Pilot Course- 09/25/17Submit Course Feedback from students- (Deliverable due 10/06/17)Write Final Report- 10/27/17